PROTECT YOUR RIGHTS
TO PAYMENT FOR CHANGED CONDITIONS
Submitted by: Robert Marconi of Stanislaw
Ashbaugh, LLP
A very recent appellate
case threatens the right of contractors to recover their extra costs for
changed conditions, when the owner has included disclamatory language in the
contract documents. In Basin Paving
Co. v. Mike M. Johnson, Inc., 107 Wn. App. 61, 27 P.3d 609 (2001), petition
for review pending, the court declared that exculpatory clauses in the
contract documents could negate a changed conditions claim as a matter of law,
despite the subsurface conditions expressly indicated in the contract
documents.
Basin Paving involved a waste water and water treatment
system project that entailed substantial excavation work. The contract designated all of the excavation
work as “unclassified excavation.” The
contract documents included all borings and geotechnical data available to the
owner. But the contract documents also
included recitals disclaiming responsibility for the reliability of the soils
information indicated in the contract documents; requiring bidders to satisfy
themselves as to the risk of adverse subsurface conditions; and defining the
scope of the excavation as requiring removal of whatever material might be
encountered during the progress of the work.
Based upon the indications in the contract documents, the
contractor anticipated some rock, but ended up excavating far more of it than
expected. Both the costs and time of the
work increased substantially beyond what had been anticipated. The contractor made claim for a changed
condition. But the owner opposed the
claim, on the theory that although the amount of rock actually encountered may
have exceeded what the contract indicated, the disclaimers prevented the
contractor from relying on the indications in the contract documents.
The trial court ruled as a matter of law in favor of the
owner, and Division 3 of the Court of Appeals affirmed. In its published opinion the appellate court
declared that regardless of whether actual conditions differed from those the
contractor reasonably anticipated based on indications in the contract
documents, the mere fact that the presence of rock was foreseeable prevented
rock -– in whatever quantity might be encountered – from constituting a
changed condition.
The Basin Paving case may prove to be a substantial
departure from pre-existing law on changed conditions in a least three
respects. First, it changes the inquiry
from whether actual conditions differed from what the contractor reasonably
anticipated to whether the actual conditions were beyond what was reasonably
foreseeable at all. Second, it allows
exculpatory clauses to “trump” the contract’s changed conditions clause, so
that bidders may not be entitled to recover even when they reasonably rely on
indications set forth in the contract documents. And third, Basin Paving permits
determination of the absence of a changed condition to be made as a matter of
law, thereby eliminating that notion of measuring the reasonableness of the contractor’s
expectations based upon the totality of indications and clauses in the
contract.
An effective response to the financial catastrophe that the
Basin Paving ruling could mean to other contractors involves an
understanding of why changed conditions clauses exist. Contrary to general belief, changed
conditions clauses are for the benefit of owners, not contractors.
Changed conditions arise from the unpredictability of
pre-existing site conditions, particularly subsurface conditions. The costs of constructing a project can vary
wildly, depending on the physical conditions encountered during the course of
the work. Pile driving through sandy
soils is cheap and easy; driving through nested cobbles and boulders can be
nearly impossible. Clay and silty soil
may be ideal for foundation work when it is dry, but can be a nightmare to work
in if saturated by unanticipated groundwater.
The importance of changed conditions, though, does not
depend primarily on whether they exist.
More fundamental is the issue of which party accepted the risk that
differing site conditions might be encountered.
Normally the owner is the party who drafts the construction
contract. Although on some private
projects the contractor has a say in the contract language, ordinarily the
owner dictates the project design and the contract terms, other than
price. On public contracts, the contract
documents are almost universally prepared solely by the owner and its agents.
As the party with the “power of the pen,” the owner can put
the entire risk of unanticipated site conditions on the contractor. Nothing in the law prevents it. In the case of Dravo Corp. v. Metro,
79 Wn.2d 214, 219-20, 484 P.2d 399 (1971), the contractor encountered severe
subsurface conditions that neither the owner nor the contractor anticipated,
and that differed from what had been found during the owner’s geotechnical
investigation. But the contractor was
denied extra compensation because the owner had disclaimed any responsibility
that the geotechnical data was representative of what the contractor should
expect, and because the prime contract had no “changed conditions” clause
providing for compensation in the event of differing site conditions.
Owners nevertheless
have found a powerful incentive not to place all risks of adverse site
conditions on the contractor. That
incentive is money. Contractors faced
with unknown and uncontrollable risks increase their prices to compensate for
contingencies. The less that is known
about the likelihood or potential severity of a risk, the higher the
contingency price will tend to be.
“Whenever dependable information on the subsurface is unavailable,
bidders will make their own borings or, more likely, include in their bids a
contingency element to cover the risk.
Either alternative inflates the costs to the Government.” Foster Construction v. , 435 F.2d 873, 886 (Ct. Cl.
1970). See Ruff v. United States,
96 Ct. Cl. 148, 164 (1942) (“[B]idders must, in order to be safe, wet their
estimates on the basis of the worst possible conditions that might be
encountered. Such a practice would be
very costly to the [owner].”).
An owner who
allocates the entire risk of changed conditions to the contractor may end up
paying far more for the work than the actual costs of construction, since the
contract price will include substantial payment for contingencies that may
never come to pass.
[With a “changed
conditions” clause] the owner expressly agrees to adjust the contractor’s
compensation if unexpected conditions are encountered. The purpose of such clauses is to make it
unnecessary for the bidder to take into account, in computing his bid,
contingencies of this kind. This results
in lower bids and in lower costs to the owner if the subsurface reveals no
unexpected conditions.
Dravo
Corp. v. Metro, 79 Wn.2d 214, 219-20, 484
P.2d 399 (1971). But see, V.C. Edwards Contracting Co. v.
Port of Tacoma, 83 Wn.2d 7, 514 P.2d 1381 (1973)(Contractor
recovered for unanticipated changed condition, despite the absence of a changed
conditions clause.).
Owners have another built-in incentive not to foist onto
the contractor all risks of adverse site conditions: The owner is uniquely well situated to assess
likely site conditions before the work begins.
The physical conditions of a site are normally evaluated through a
geotechnical investigation. It may
involve borings, test pits, laboratory analyses, research of earlier
construction on the same site or nearby areas, and interpretation by
professionals of the known geological site conditions. The investigation may take weeks to perform,
and more weeks to digest. Its results
may indicate that design revisions for the project are in order, either to make
it buildable in light of adverse aspects of the site, or to make construction
more cost effective. Indeed, a
reasonably thorough investigation of site conditions may be needed before a
project design can even proceed.
The owner and its professionals are the only parties to a
construction project in the position to decide how much time and resources
should be dedicated to a geotechnical investigation before the project is
designed and let for bidding. The more
time and money the owner devotes to the investigation, the more suitable will
be the project’s design to actual site conditions, and the more certain will be
the project’s cost because the risk of unknown conditions is reduced. By taking responsibility for a site
investigation, and for some degree of risk that actual conditions will not be
worse than the pre-bid investigation suggests, the
owner can make a cost/benefit decision on how much time and money to dedicate
to the investigation and design phase of a project.
An owner who merely places all risk of adverse site
conditions on the contractor forfeits that opportunity. In evaluating a project for bidding,
contractors have very limited incentive to put substantial effort into
investigating an owner’s site. Potential bidders normally get nothing for the
time and money they dedicate to bidding, other than the possibility of eventual
contract award. Construction contractors
also do not normally have geotechnical investigation equipment,
or professionals on staff to operate it and interpret the results. Moreover, leaving responsibility for site
investigation to potential bidders is wasteful, since the results of any one
contractor’s investigation will not be shared with contractors preparing
competing bids. Consequently, owners
have found it is in their own interest to decide how much pre-bid investigation
may be appropriate, to perform it prior to preparing contract documents, and to
accept some level of risk against other, unanticipated site conditions.
The “changed
conditions” clause is the contract mechanism to allocate the risk of adverse
site conditions between the owner and the contractor. The changed conditions clause works in
conjunction with the indications of conditions shown or reasonably inferred
from the contract documents.
The two elements
work together; the presence of the changed conditions clause works to reassure
bidders that they may confidently rely on the logs and need not include a
contingency element in their bids.
Reliance is affirmatively desired by the Government, for if bidders feel
they cannot rely, they will revert to the practice of increasing their bids.
The
purpose of the changed conditions clause is thus to take at least some of the
gamble on subsurface conditions out of bidding.
Bidders need not weigh the cost and ease of making their own borings
against the risk of encountering an adverse subsurface, and they need not
consider how large a contingency should be added to the bid to cover the
risk. They will have no windfalls and no
disasters. The Government benefits from more accurate bidding, without
inflation for risks which may not eventuate.
It pays for difficult subsurface work only when it is encountered and
was not indicated in the logs.
Foster
Construction v. United
States,
435 F.2d 873, 886 (Ct. Cl. 1970).
While borings, gradation results, laboratory tests, site
descriptions, and other geotechnical information can all furnish indications of
conditions for the contractor to expect, they are routinely accompanied by
clauses conditioning bidders’ ability to rely on those indications. Those clauses approach the subject in
different ways. Some disclaim outright
the accuracy or reliability of the information presented. Others affirm its accuracy, but disclaim any
responsibility for relying on it. Still
others call for bidders to perform their own site investigations.
In the event of a dispute, none of these clauses will be
disregarded. But at the same time, none
of them is likely to be deemed legally dispositive. Instead, each will be weighed according to
its terms, but also in the context of the representations and indications that
the contract documents do furnish to the contractor. In other words, whether a differing site
condition exists will remain an issue of fact, and disclamatory or cautionary
language in the contract documents are additional facts to weigh on that
issue. See Bignold
v. King County, 65 Wn.2d 817, 821-22, 399 P.2d 611 (1965) (Whether
differing site condition exists is a question of fact, and will be found if a
condition could not reasonably be anticipated, “despite admonitory or
exculpatory phrases”.).
One such clause, nearly universal to public contracting,
requires bidders to perform their own site investigation. WSDOT Standard Specification 1-02.4(1) (2000
ed.) is typical of these provisions:
The bidder shall carefully examine the
bid documents as defined in Section 1-01.2.
Submittal of a bid shall be conclusive evidence that the bidder has made
these examinations and understands all requirements for the performance of the
completed work. The bidder further
warrants, agrees, and acknowledges by submitting a bid that it . . . [h]as
satisfied itself as to the character, quality, and quantity of surface and
subsurface materials or obstacles to be encountered insofar as this information
is reasonably ascertainable from an inspection of the work site (including
material sites) as well as from the bid documents and other information made a
part of this contract . . . .
The bidder agrees that the Contracting
Agency shall not be liable to it on any claim for additional payment or
additional time or any claim whatsoever if the claim directly or indirectly
results from the bidder’s failure to investigate and familiarize itself
sufficiently with the conditions under which the contract is to be performed.
Conducting firsthand a site investigation is good
construction practice. A contractual
reminder that bidders should do so hurts no one, and is a simple precaution
against slap-dash bid preparation. Even
without such an admonitory clause, a contractor would have difficulty
prevailing on a claim over a site condition that a reasonable site inspection
would have revealed. Both Type I and
Type II claims require the contractor to prove that the condition was not
anticipated and that the contractor should not reasonably have anticipated the
condition.
At the other end of the exculpatory scale are clauses that
purport to eviscerate whatever significance indications of site conditions in
the contract documents might otherwise have.
The disclamatory clause at issue in Dravo Corp. v. Metro, 79
Wn.2d 214, 484 P.2d 399 (1971), presents a fine example:
Subsoil investigations, including
underwater borings, were carried out in the vicinity of the interceptor sewer
alignment prior to advertisement of the contract. Reports giving the results of these
investigations may be examined at the Municipality’s offices. These investigations were carried out for
design purposes only, and are not considered adequate for construction.
The Municipality does not warrant the
correctness of the soil investigations, or of any interpretation, deduction or
conclusion given in the report relative to subsurface conditions. The bidder shall make his own deductions and
conclusions as to the nature of the materials to be excavated, the difficulties
of making and maintaining the required excavations, the difficulties which may
arise from subsurface conditions, and of doing any other work affected by the
subsurface conditions, and shall accept full responsibility therefore.
No extra payment will be made over and
above the contract price on account of any difference between the information
relating to soil and foundation conditions provided by the Municipality and the
conditions disclosed at the site of the work during the progress of the
contract.
79 Wn.2d at 215-16
(emphasis added). Such clauses undercut
to the point of contradiction the notion of changed conditions, when the
contract also contains a changed conditions clause (which the contract in Dravo
did not).
More typical of disclamatory clauses are provisions
reciting that information furnished to bidders is “for information only,” or is
accurate solely to the extent of the sample tested, and cannot be relied upon
to indicate conditions anywhere else on the site. The WSDOT specs contain such a clause:
If the Contracting Agency has made
subsurface investigation of the site of the proposed work, the boring log data
and soil sample test data accumulated by the Contracting Agency will be made
available for inspection by the bidders. . . .
The Contracting Agency specifically
makes no representations, guarantees, or warranties as to the condition,
materials, or proportions of the materials between the specific borings
regardless of any subsurface information the Contracting Agency may make
available to the prospective bidders.
Standard Specifications §
1-02.4(2) (2000 ed.).
Where the contract includes a changed conditions clause,
courts do not routinely allow the owner to offer with one hand (by including
indications of site conditions in the contract documents and a promise to pay
for differing site conditions), while taking away with the other (by also
inserting disclamatory or exculpatory language in the contract).
It was not incumbent upon the
plaintiff, prior to submitting its bid and entering into the contract, to
conduct its own investigation in order to ascertain the truth or falsity of the
defendant’s positive assertions regarding subsurface conditions . . ., even
though the contract contained a general condition stating that “The Contractor
further acknowledges that he has satisfied himself as to the character, quality
and quantity of surface and sub-surface materials to be encountered insofar as
this information is reasonably ascertainable from an inspection of the site,
including all exploratory work done by the Government,” and also contained a
technical provision stating that “the Government does not guarantee that
materials other than those disclosed by the explorations [i.e. the test
borings] will be encountered.”
Morrison-Knudsen
Co. v. United States, 345 F.2d 535, 539 (Ct. Cl. 1965).
The furnishing by the owner of detailed subsurface data is
in effect an invitation for potential contractors to consider it in pricing
their bids. Indeed, a potential bidder
could be faulted for not considering the significance of that data on the
anticipated costs of the work. To the
extent the contract documents and the site information furnished in conjunction
with them invite or require consideration by the contractor, they may be deemed
to indicate anticipated conditions, even in the face of other, disclamatory
contract language.
The effect of an
actual representation is to make the statements of the Government binding upon
it, despite exculpatory clauses which do not guarantee the accuracy of a
description.
Woodcrest
Construction Co. v. United
States,
408 F.2d 406, 410 (Ct. Cl. 1969).
For example, in United Contractors v. United States,
368 F.2d 585 (Ct. Cl. 1966), the government performed a subsurface
investigation, and furnished its boring logs and related information to
prospective bidders. The contract
documents recited that the information furnished was to assist bidders in
ascertaining the character of conditions to be encountered, but the contract
explicitly disclaimed any responsibility that the subsurface indications were
representative of what the contractor would encounter. Nevertheless, the court found entitlement for
a changed condition:
It is true that Provision 1-07 also
provided that "the Government does not guarantee that materials other than
those disclosed by the explorations will not be encountered, or that the
proportions of the various materials will not vary from those indicated by the
logs of the explorations." But we
have held, in comparable circumstances, that broad exculpatory clauses
(identical in effect with this one) cannot be given their full literal reach,
and "do not relieve the defendant of liability for changed conditions as
the broad language thereof would seem to indicate." Fehlhaber Corp. v. United States, 138
Ct. Cl. 571, 584, 151 F. Supp. 817, 825 (1957), cert. denied, 355 U.S. 877. As Fehlhaber said, general portions of
the specifications should not lightly be read to override the Changed
Conditions clause. Ibid. It takes clear and unambiguous language to do
that, for "the provision sought to be eliminated, or subordinated, is a
standard mandatory clause of broad application * * *." Thompson Ramo Wooldridge
Inc. v. United States,
175 Ct. Cl. 527, 536, 361 F. 2d 222, 228 (1966).
368 F.2d at 598.
For examples of cases
finding a changed condition based on indications furnished to the contractor,
notwithstanding disclaimers that all such data was for “information only” and
not to relieve bidders from making their own investigation and determination of
conditions to expect, see Bignold v. King County, 65 Wn.2d 817, 821-22,
399 P.2d 611 (1965); Walla Walla Port District v. Palmberg, 280 F.2d 237
(9th Cir. 1960); Hersey Gravel Co. v. State, 305 Mich. 333, 9 N.W.2d 567
(1943).
A particularly cogent discussion of the reasons to
subordinate exculpatory language to express indications of site conditions
furnished to the contractor is found in Haggart Construction Co. v. State
Highway Commission, 427 P.2d 686 (Montana 1967):
Certainly
the exculpatory clauses are inconsistent with the statements made concerning
gravel sources and the purpose for which such statements were rendered. Basic notions of fair play, as well as sound
principles of public policy, require the contradiction to be resolved in favor
of Haggart in this case.
Individual
contractors are in a poor bargaining position with respect to the type of road
construction contract involved here. It
would be unreasonable to suppose that prospective bidders could obtain more
equitable terms, since the customary practice of appellant seems to include the
use of these exculpatory clauses. The
contractor is inevitably in a "take it or leave it" situation. The danger to public interests, implicit in
such a case, is pointed out in Ozark Dam Constructors v. United States,
D.C., 127 F.Supp. 187, 190:
“A contract for
immunity from the harmful consequences of one's own negligence always presents
a serious question of public policy.
That question seems to us to be particularly serious when, as in this
case, if the Government got such an immunity, it
bought it by requiring bidders on a public contract to increase their bids to
cover the contingency of damages caused to them by the negligence of the
Government's agents. Why the Government would want to buy and pay for such an immunity is hard to imagine. If it does, by such a provision in the contract,
get the coveted privilege, it will win an occasional battle, but lose the war.”
427 P.2d at 689.
Judicial resolution of the tension between affirmative site
indications in the contract documents, a changed conditions clause, and
disclamatory language is well illustrated by the case of Kit-San-Azusa v. United States,
32 Fed. Cl. 647 (1995). The first stage
of the project there required the contractor to construct a sheet pile
cofferdam, and perform mass excavation for a largely-underground pumping plant. Test borings disclosed predominantly silts,
sand, and gravel soils, with (in a few borings) isolated cobbles. None of the borings identified boulders.
In attempting to drive sheet piling, though, the contractor
encountered immovable obstructions, which almost certainly were boulders or
nested cobbles. In subsequently
excavating much of the site, many boulders were unearthed, as were large
volumes of cobbles. The contractor
submitted claim for a changed condition.
The government defended on two theories. First, it pointed out that while the specific
borings showed no boulders and few cobbles, the generic site description told
the contractor to expect glacial outwash deposits geotechnically defined as “QW
deposits”: “[Qw material is] generally composed
of a heterogenous mixture of silt, sand, gravel, cobbles, and boulders.” So, the government argued, it had warned
bidders to expect boulders. Second, the
government argued that while the borings themselves were represented to be
accurate for the small cylinder of material extracted and tested, the
government made no representation that any of the borings were representative
of surrounding soils. Therefore, the
government argued, the lack of indication of boulders and nested cobbles in
specific site data given to bidders could not serve as the basis of a claim of
a differing site condition.
The court’s resolution of the dispute reflects a balancing
of all of the relevant portions of the contract, weighing them particularly in
the context of the importance a prudent bidder would attach:
While the contractor cannot ignore the
site description, it is entitled to place greater reliance on boring logs if
they are numerous and well spaced, as these were. The specifications’ reference to boulder,
even at the site-specific level, was due to the general classification type of
the soil. The Government places too much
emphasis on the general classification of the soil and not enough on what was
specifically found, at least insofar as what was shown the contractor in the
boring logs. That there were, in a
technical sense, boulders in the ground at the site is apparent from the
results of excavation at Phase II. Rock
of sufficient size to qualify as boulders was definitely present. . . .
The court concludes that to the extent
there was boulder, and that the boulders interfered with construction, KSA
encountered a differing site condition.
To hold to the contrary means that a contractor has to assume from the
possibility of boulder in a general type of geologic stratum, that boulder
could be encountered at any point, despite the lack of indications in the
boring logs. Such an assumption would be
nearly impossible to factor into a bid.
Richard Galster, a private consulting engineering geologist, testified
for the Government that one cannot extrapolate more than a foot from a boring
log. Under that approach, the site could
have had no boulders, or, according to the Government, it could be virtually
solid boulder. Would there be no
differing site condition so long as there was no boulder within a few feet of
any of the boring holes? Clearly at some
point the degree of difficulty due to boulder becomes a differing site
condition. That point was reached here.
32 Fed. Cl. at 651 (1995).
These authorities reflect decades of careful balancing
between affirmative indications in the contract documents and purported efforts
at disclaiming their significance.
Because the underlying purpose of a changed conditions clause is for the
owner’s benefit (reducing the overall costs of performance), language
purporting to distance the owner from responsibility for the accuracy of
conditions indicated in the contract has tended to be viewed with disfavor, if
not outright discarded.
But the recent Basin Paving case threatens to
overturn those well-settled principles, and largely nullify changed conditions
clauses as a risk-shifting device. If
the holding of the case prevails as controlling Washington law, and if owners continue to
insert disclamatory language in their contract documents, a changed conditions
clause will offer little protection to the contractor from escalating costs
where conditions prove to be more adverse than expected.
The prudent
contract can protect against that outcome, at least on private projects, by expressly
negotiating how much risk shifting the owner is willing to assume, and
conversely how much contingency the owner is willing to pay for. By reminding the owner that to the extent the
contractor assumes the risk of adversity he will adjust his pricing upward, the
owner can make an informed decision of whether to abide by the promise of a
changed conditions clause, or else agree that changed conditions will not
warrant extra compensation, in which case the contractor should price the
initial contract work to reflect the risk of adverse conditions.