Not required |
Not required |
| |
|
When |
Not required |
Within 90 days of the last supply of labor or materials for which
claim is made. 40 U.S.C. § 270b(a) |
|
What |
Not required |
Accurate written statement of amount claimed, name of party for whom
unpaid materials were furnished or labor performed, and statement that
claimant looks to prime contractor for payment. 40 U.S.C. § 270b(a) |
|
How |
Not required |
By any means which provides written verification of delivery by a
third-party. (Prepaid registered mail or service by a process server is
recommended). 40 U.S.C. § 270b(a) |
| Suit on Claim |
No sooner than 90 days after last supply of labor or
materials for which claim is made, and no later than one year
after last supply of labor or materials to the project. 40 U.S.C. §
270b |
No sooner than 90 days after last supply of labor or
materials for which claim is made, and no later than one year
after last supply of labor or materials to the project. 40 U.S.C. §
270b |