Mechanic's & Materialmen's Lien Claims |
| |
| |
|
When |
Within 60 days after commencement of furnishing materials or
equipment. RCW 60.04.031(1)
In the cases of a direct contract with the owner on residential
projects with less than 4 units and commercial projects with a total
contract price of less than $60,000, a separate "Notice to
Owner" is required. RCW
18.27.114. |
Within 10 days after commencement of furnishing materials or
equipment. RCW 60.04.031(1) |
|
What |
Written notice including information called for by statutory form set
out in RCW
60.04.031(4). |
Written notice including information called for by statutory form set
out in RCW
60.04.031(4). |
|
How |
To owner and prime contractor by certified mail, registered mail, or
hand delivery (with signed receipt). RCW 60.04.031(1) |
To owner and prime contractor by certified mail, registered mail, or
hand delivery (with signed receipt). RCW 60.04.031(1) |
| |
|
When |
Within 90 days after ceasing to furnish labor, materials, or
equipment. RCW 60.04.091 |
Within 90 days after ceasing to furnish labor, materials, or
equipment. RCW 60.04.091 |
|
What |
Written Claim of Lien furnishing information required by statutory
form set out in RCW 60.04.091. |
Written Claim of Lien furnishing information required by statutory
form set out in RCW 60.04.091. |
|
How |
Record Claim of Lien in county where project is located, and furnish
copy to owner by certified mail, registered mail, or hand delivery (with
signed receipt) within 14 days of recording. RCW 60.04.091. |
Record Claim of Lien in county where project is located, and furnish
copy to owner by certified mail, registered mail, or hand delivery (with
signed receipt) within 14 days of recording. RCW 60.04.091. |
|
Suit on Claim |
Suit must be brought within 8 months of recording the Claim of Lien. RCW
60.04.141. |
Suit must be brought within 8 months of recording the Claim of Lien. RCW
60.04.141. |