When |
Within 60 days after commencement of furnishing labor, materials, or
equipment; the notice won't protect rights for earlier-furnished
materials and labor. First tier subs and suppliers may not need to
provide pre-claim notice. RCW 60.28.015 |
Within 10 days of first supply of materials or labor. First tier subs
and suppliers may not need to provide pre-claim notice. RCW 39.08.065 |
|
What |
Written notice describing materials, supplies and equipment being
furnished, naming the subcontractor ordering them, and stating that
claim for payment may be made against retainage. RCW 60.28.015 |
Written notice describing materials, supplies and equipment being
furnished, naming the subcontractor ordering them, and stating that
claim for payment may be made against prime contractor and its bond. RCW 39.08.065 |
|
How |
To prime contractor by certified mail, registered mail, or hand
delivery (with receipt signed by contractor). RCW 60.28.015 |
To prime contractor by mail or hand delivery (proof of receipt
recommended). RCW 39.08.065 |
| |
|
When |
Within 45 days of "completion of [prime] contract work."
RCW 60.28.011(2) |
Within 30 days after final acceptance of project by the owner. RCW
39.08.030 |
|
What |
Written statement of claim addressed to the owner, identifying the
claimant and describing the work, materials or supplies for which claim
is made, naming the prime contractor and stating claim is made against
contractor's retainage. The claimant must sign the claim. The statutory
form for bond claims, contained in RCW
39.08.030, modified to state
claim is made against the contractor's retainage, is recommended. RCW
60.28.010 |
Written statement of claim addressed to the owner, identifying the
claimant and describing the work, materials or supplies for which claim
is made, naming the prime contractor and stating claim is made against
contractor's bond. The claimant must sign the claim. The statutory form
is recommended. RCW
39.08.030 |
|
How |
File claim with owner within 45 days of completion of work in the
manner provided in RCW
39.08.030. (Written proof of receipt
recommended.) Claimant should provide a copy to contractor by certified
mail, registered mail, or hand delivery (written proof of receipt
recommended).
RCW 60.28.011(2) |
File claim with owner. (Written proof of receipt recommended.)
Claimant should provide a copy to contractor and its bond company by
certified mail, registered mail, or hand delivery (written proof of
receipt recommended). RCW
39.08.030 |
|
Suit on Claim |
Suit must be brought within 4 months of filing claim. The claim may
be refiled within four month period, but not if 45 days have passed
after completion of prime contract work.
RCW 60.28.011(2) and RCW
60.28.030 |
Suit should be brought within time prescribed in the bond, and in no
event later than 6 years |