Claims on Federal Bonds

Submitted by: Stanislaw, Ashbaugh, LLP

 

1st Tier Subcontractors and Suppliers

2nd Tier Subcontractors and Suppliers

 

Pre-Claim Notice:

 

Not required

Not required

 

Notice of Claim:

When

Not required

Within 90 days of the last supply of labor or materials for which claim is made. 40 U.S.C. § 270b(a)

What

Not required

Accurate written statement of amount claimed, name of party for whom unpaid materials were furnished or labor performed, and statement that claimant looks to prime contractor for payment. 40 U.S.C. § 270b(a)

How

Not required

By any means which provides written verification of delivery by a third-party. (Prepaid registered mail or service by a process server is recommended). 40 U.S.C. § 270b(a)

Suit on Claim

No sooner than 90 days after last supply of labor or materials for which claim is made, and no later than one year after last supply of labor or materials to the project. 40 U.S.C. §270b

No sooner than 90 days after last supply of labor or materials for which claim is made, and no later than one year after last supply of labor or materials to the project. 40 U.S.C. §270b